Key takeaways

A payment schedule is due within the time set by your contract, or 10 business days after the payment claim is served — whichever is earlier, with no flexibility built in. Miss it and you're liable for the full claimed amount, though a notice of intention to apply for adjudication can still give you a second chance to respond.

On this page

A payment schedule is your formal response to a payment claim. It states the amount you propose to pay and, if that's less than what was claimed, the reasons why.

The deadline

A payment schedule must generally be provided within the time required by your contract, or 10 business days after the payment claim is served — whichever is earlier. There's no flexibility built into this deadline.

What happens if you miss it

If a payment schedule isn't provided in time, you become liable to pay the full claimed amount. The claimant can then pursue recovery in court — where you're barred from raising any cross-claim or defence arising under the contract — make an adjudication application, or serve a notice of intention to suspend work. You do get one further chance to respond: if the claimant serves a notice of intention to apply for adjudication, you then have 5 business days to provide a payment schedule, and if you do, the dispute can still proceed through adjudication.

If a claim has just landed, call us straight away — timing is everything.

Call NowGet Claim Review