Guide
The due date drives interest, suspension rights and every deadline after it. Here's how to work it out correctly.
Check your contract first: most commercial contracts set their own due date. Where a contract is silent, the Act's fallback provisions apply, and getting this date right matters because interest, suspension rights and later deadlines all flow from it.
Getting the due date wrong on a payment claim can cost you weeks, or your footing in a later dispute. Under the Building and Construction Industry Security of Payment Act 1999 (NSW), the due date is not simply when you would like to be paid. It is a defined trigger that determines when interest starts running, when you can suspend work for non-payment, and how later deadlines in the process are calculated.
The due date for a progress payment is the date by which the claimed amount becomes payable. It is distinct from the date you serve the payment claim, and distinct from the payment schedule deadline a respondent has to formally dispute it. Confusing these three dates is one of the most common early mistakes we see.
Most commercial construction contracts set their own payment terms, for example payable within a fixed number of days of a valid invoice, or a set date each month. Where the contract deals with the matter, that contractual date generally governs, subject to the Act overriding unfair time-bar and "pay when paid" style provisions that try to make payment conditional on events outside the claimant's control.
If a construction contract does not provide for a due date, the Act supplies a fallback timeframe. The precise statutory default has been the subject of legislative amendment over the years, so if your contract does not clearly deal with payment timing, this is exactly the kind of detail worth confirming against the current, in-force version of the Act before you rely on a calculated date.
The due date affects when unpaid amounts start accruing interest at the rate prescribed under the Act, your ability to suspend work for non-payment (which generally requires the amount to be overdue), and how later deadlines in the payment claim and adjudication process are calculated. Because so much downstream timing depends on this one date, an error here tends to compound rather than stay contained.
Head contracts and subcontracts on major projects across Parramatta, the Hills district and Blacktown growth corridors typically run on standard industry contract forms with detailed payment schedules built in, which usually makes the due date a matter of reading the contract correctly. For our broader construction law services in these areas, see Archer Lawyers' Parramatta, Hills district and Blacktown pages.
Smaller regional builders and subcontractors around Newcastle, Wollongong and the Central Coast are more likely to be working under a short-form or verbal contract, which is exactly when the statutory default provisions become the operative rule rather than a fallback that never gets used. For our broader construction law services in these areas, see Archer Lawyers' Newcastle, Wollongong and Central Coast pages.
No. The due date is when payment becomes payable. The payment schedule deadline is the separate, shorter window a respondent has to formally dispute a claim. The two are calculated differently and confusing them is a common error.
Not entirely. The Act overrides contract terms that try to unreasonably delay payment or make payment conditional on events outside the claimant's control, such as the head contractor being paid first.
Working from an incorrect due date can throw off your interest calculation and your assessment of when you're entitled to suspend work. It rarely invalidates a claim outright, but it can weaken your position if challenged.
No. The due date is fixed by the contract or the Act. A dispute over the amount doesn't move the due date, though it does open the payment schedule and, potentially, the adjudication process.
Get advice before you act on an assumption. A short review of the payment clause against the Act is usually enough to confirm the correct date with certainty.
If you're not confident about the due date on a current or upcoming claim, get it checked before you rely on it. Contact our team for a free assessment.